Blog

Feb 23
Package 1 - Raichur - Gadwal

Progress Status – Feb’23

CGM(Tech) RO, PD and IE visit at Km. 203+500
CGM(Tech) RO, PD and IE visit at Km. 203+500
CGM(Tech) RO, PD and IE visit at Km. 241+087
CGM(Tech) RO, PD and IE visit at Km. 241+087
Rebound hammer testing for RE Panels
Rebound hammer testing for RE Panels
FDD testing for embankment at Km. 203+500
FDD testing for embankment at Km. 203+500
Borrow area sampling at Km. 204_200 RHS
Borrow area sampling at Km. 204_200 RHS
NDT testing for RE Panels
NDT testing for RE Panels