MEIL JULEKAL ROADWAYS PRIVATE LIMITED
About Project
National Highways Authorities of India (NHAI) has appointed MEIL Julekal Roadways Private Limited, as the Concessionaire for the design and built of the 38.200 Km Six Laning of of NH-150C from Julekal village ( Design Chainage KM 242+200 ) to Kurnool Town Terminating on NH-40 ( Design Chainage KM 280+400 ) (Length 38.20 KM ) as part of Solapur-Kurnool-Chennai Economic Corridor on Hybrid annuity Mode Under Bharatmala Pariyojna in the state of Telangana. The alignment is Greenfield passing through Cultivation area falls in the state of Telangana and Andhra Pradesh. The entire project road broadly passes through plain terrain. Most of the land use pattern falls under Forest barren/agricultural land exists on both side of the project road and also built-up area. The alignment passes through Tungabhadra and Handri River with Major Bridges. The pavement is entirely of flexible type and rigid type at Toll Plaza
Note: The duration for the construction of the project is 730 days from the appointed date with 15 years of operation and maintenance period.
Julekal - Kurnool Package two
Scope of the Project
60/10 No’s
Box/Pipe Culverts
06 No’s
Vehicular Underpass
25 No’s
Light Vehicular Underpass
12 No’s
Minor Bridges
02 No’s
Major Bridge
Project details and Timeline
Construction of Six-Lane Access Controlled Greenfield Highway Section of NH-150C from Julekal village ( Design Chainage KM 242+200 ) to Kurnool Town Terminating on NH-40 ( Design Chainage KM 280+400 ) (Length 38.20 KM ) as part of Solapur-Kurnool-Chennai Economic Corridor on HAM Under Bharatmala Pariyojna in the state of Telangana ( Package-2)
Role/Type | Details |
---|---|
EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
Independent Engineer | M/s. Satra Services and Solution Pvt. Ltd. in JV with M/s Rodic Consultants Pvt. Ltd |
Agreement Date | 20th may 2022 |
Appointed Date | 04th January 2023 |
Maintenance Period | 15 Years after commencing |
COD Construction Period | 24 Months (730 days) from Appointed Date |
Project Cost | 943.5 Crs. |
Project highlights
- Six-Lane Access Controlled Greenfield Highway
- NH-150C from KN/TS Border Start from Raichur - Gadwal Road
- Part of Solapur-Kurnool-Chennai Economic Corridor
- Comes Under Bharatmala Pariyojana
- Provides safe travel and reduce travel time