WMM TOP at ch 217+380 to 217+540 in presence of TL sir and IE teamCH : 222+160 (LVUP ) excavation work has been halted by the villagers, and they are willing to resume discussions after consulting with our local MLA (Member of Legislative Assembly) to determine a more suitable location206+500 to 206+800 BHS sub grade top layerDBM 1st Laying is in Progress from ch. 223.040 To 223.240 LHSDBM Top laying in presence of TL & SQME at Ch 214+860 to 215+060
DBM 1st layer laying at 215060 to 215340 RHS in progressDBM laying from Km. 224+980 to Km. 225+080