MEIL GADWAL JULEKAL ROADWAYS PRIVATE LIMITED
About Project
National Highways Authorities of India (NHAI) has appointed MEIL Gadwal Julekal Roadways Private Limited, as the Concessionaire for the design and built of the 39.300 KM Six Laning of KN/TS Border (Start from Raichur – Gadwal Road) (Design Chainage KM 202+900) to Julekal Village (Design Chainage KM 242+200) as part of Solapur-Kurnool-Chennai Economic Corridor on Hybrid annuity Mode under Bharatmala Pariyojana in the state of Telangana. The alignment is Greenfield passing through Cultivation area and broadly passes through plain terrain. Most of the land use pattern falls under Forest barren/agricultural land exists on both side of the project road and also built-up area. The pavement is entirely of flexible type and rigid type at Toll Plaza.
Note: The duration for the construction of the project is 730 days from the appointed date with 15 years of operation and maintenance period.
Raichur - Gadwal Package one
Scope of the Project
68/2 No’s
Box/Pipe Culverts
2 No’s
Vehicular Underpass
37 No’s
Light Vehicular Underpass
34 No’s
Minor Bridges
1 No’s
Major Bridge
Project details and Timeline
Construction of Six-Lane Access Controlled Greenfield Highway Section of NH-150C from KN/TS Border (Start from Raichur – Gadwal Road) (Design Chainage KM 202+900) to Julekal Village (Design Chainage Km 242+200) (Length 39.30 KM) as part of Solapur-Kurnool-Chennai Economic Corridor on HAM Under Bharatmala Pariyojana in the state of Telangana (Package-1)
Role/Type | Details |
---|---|
EPC Contractor | M/s. Megha Engineering & Infrastructures Limited |
Independent Engineer | M/s. Satra Services and Solution Pvt. Ltd. in JV with M/s Rodic Consultants Pvt. Ltd |
Agreement Date | 09th may 2022 |
Appointed Date | 04th January 2023 |
Maintenance Period | 15 Years after commencing |
COD Construction Period | 24 Months (730 days) from Appointed Date |
Project Cost | 779.5 Crs. |
Project highlights
- Six-Lane Access Controlled Greenfield Highway
- NH-150C from KN/TS Border Start from Raichur - Gadwal Road
- Part of Solapur-Kurnool-Chennai Economic Corridor
- Comes Under Bharatmala Pariyojana
- Provides safe travel and reduce travel time
Recent updates
Construction of bridge is completed at Julekal
Construction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of…