About Project

 

National Highways Authorities of India (NHAI) has appointed MEIL Gadwal Julekal Roadways Private Limited, as the Concessionaire for the design and built of the 39.300 KM Six Laning of KN/TS Border (Start from Raichur – Gadwal Road) (Design Chainage KM 202+900) to Julekal Village (Design Chainage KM 242+200) as part of Solapur-Kurnool-Chennai Economic Corridor on Hybrid annuity Mode under Bharatmala Pariyojana in the state of Telangana. The alignment is Greenfield passing through Cultivation area and broadly passes through plain terrain. Most of the land use pattern falls under Forest barren/agricultural land exists on both side of the project road and also built-up area. The pavement is entirely of flexible type and rigid type at Toll Plaza.

 

 

Note: The duration for the construction of the project is 730 days from the appointed date with 15 years of operation and maintenance period.

Raichur - Gadwal Package one

Scope of the Project

68/2 No’s

Box/Pipe Culverts

2 No’s

Vehicular Underpass

37 No’s

Light Vehicular Underpass

34 No’s

Minor Bridges

1 No’s

Major Bridge

Project details and Timeline

Construction of Six-Lane Access Controlled Greenfield Highway Section of NH-150C from KN/TS Border (Start from Raichur – Gadwal Road) (Design Chainage KM 202+900) to Julekal Village (Design Chainage Km 242+200) (Length 39.30 KM) as part of Solapur-Kurnool-Chennai Economic Corridor on HAM Under Bharatmala Pariyojana in the state of Telangana (Package-1)

HTML Table Generator
Role/Type Details
EPC Contractor  M/s. Megha Engineering & Infrastructures Limited
Independent Engineer  M/s. Satra Services and Solution Pvt. Ltd. in JV with M/s Rodic Consultants Pvt. Ltd 
Agreement Date  09th may 2022 
Appointed Date   04th January 2023 
Maintenance Period  15 Years after commencing 
COD Construction Period  24 Months (730 days) from Appointed Date 
Project Cost  779.5 Crs. 
Project photos

Project highlights

  • Six-Lane Access Controlled Greenfield Highway
  • NH-150C from KN/TS Border Start from Raichur - Gadwal Road
  • Part of Solapur-Kurnool-Chennai Economic Corridor
  • Comes Under Bharatmala Pariyojana
  • Provides safe travel and reduce travel time

Recent updates

Construction of bridge is completed at Julekal

Construction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of bridge is completed at JulekalConstruction of…